Failure Event - US, CA, Moss Landing - 4 Sep 2021

From EPRI Storage Wiki
Revision as of 00:54, 7 October 2024 by Jthompson (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Overview

Event DetailsSMW-Info-button.png
Location: US, CA, Moss Landing
Capacity (MW): 300
Capacity (MWh): 1,200
Battery Module: LG Energy Solution
Integrator: Fluence
Application: Solar Integration
Installation: Power Plant
Enclosure Type:
Event Date: 4 September 2021
System Age (yr): 0.8
Extent of Damage: Scorched racks, melted wires
State During Accident:
Description:
Root Cause: Integration, Construction, or Assembly
Failed Element: Balance of plant
Source: Vistra
Additional Resources: [https://pv-magazine-usa.com/2021/09/07/moss-landing-energy-storage-facility-knocked-offline-after-batteries-overheat PV Magazine
Vistra Findings and Corrective Actions Report]
Note: Missing values in this table reflect unknowns.

If you have any details or corrections you would like to contribute to the database please reach out to our Storage Safety email.