Difference between revisions of "Template:Deployment RACI Nav Table"

From EPRI Storage Wiki
Jump to navigation Jump to search
(Created page with "<noinclude> This is the "Deployment RACI Nav Table" template used to quickly and concisely add this RACI Nav Table to a page. To use this, place <pre>{{Deployment RACI Nav Table}}</pre> in the desired location on a page. == Template preview == </noinclude> {| class="wikitable" |+ ! Chapter 4: Deployment & Integration - Outline and RACI Matrix ! Project Mgmt. ! Engineering ! Safety ! Operations ! Legal ! IT / OT Cybersecurity ! Maintenance / Service |- | colspan="8" |...")
 
 
(9 intermediate revisions by 2 users not shown)
Line 5: Line 5:


== Template preview ==
== Template preview ==
</noinclude>
</noinclude>{| class="wikitable"
 
{| class="wikitable"
|+
|+
! Chapter 4: Deployment & Integration - Outline and RACI Matrix
! Chapter 4: Deployment & Integration - Outline and RACI Matrix
Line 15: Line 13:
! Operations
! Operations
! Legal
! Legal
! IT / OT Cybersecurity
! IT / OT / Cybersecurity
! Maintenance / Service
! Land / Environment
! Community Affairs
! Supply Chain
! Corporate Mgmt.
|-
|-
| colspan="8" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Handoff_to_Operations|'''Handoff to Operations''']]
| colspan="11" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Engineering_&_Permitting|'''Engineering and Permitting''']]
|-
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Operational_Data_Management|Operational Data Management]]
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Site_Engineering|Site Engineering]]
| style="text-align: center;" | A
| style="text-align: center;" | A
| style="text-align: center;" | R
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | -
| style="text-align: center;" | -
| style="text-align: center;" | C
| style="text-align: center;" | -
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#System_Engineering|System Engineering]]
| style="text-align: center;" | A
| style="text-align: center;" | R
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | -
| style="text-align: center;" | C
| style="text-align: center;" | -
|-
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Optimization_of_the_BESS|Optimization of BESS]]
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Permitting_and_Applicable_Codes,_Standards,_and_Regulations_(CSRs)|Permitting]]
| style="text-align: center;" | A
| style="text-align: center;" | A
| style="text-align: center;" | R
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | I
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Factory_Acceptance_Testing|Factory Acceptance Test]]
| style="text-align: center;" | A
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | -
| style="text-align: center;" | -
| style="text-align: center;" | I
| style="text-align: center;" | R
| style="text-align: center;" | I
| style="text-align: center;" | I
|-
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Operations%E2%80%99_Coordination_with_Maintenance|Operations' Coordination with Maintenance]]
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Shipping_and_Receiving|Shipping and Receiving]]
| style="text-align: center;" | A
| style="text-align: center;" | A
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | -
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | I
|-
| colspan="11" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Installation_and_Integration|'''Installation and Integration''']]
|-
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Maintenance|Maintenance]]
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Construction_Management|Construction Management]]
| style="text-align: center;" | A
| style="text-align: center;" | A
| style="text-align: center;" | C/R
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C/R
| style="text-align: center;" | C
| style="text-align: center;" | -
| style="text-align: center;" | R
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | -
| style="text-align: center;" | -
| style="text-align: center;" | C/R
|-
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Recommissioning|Recommissioning]]
| [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Commissioning|'''Commissioning''']]
| style="text-align: center;" | A
| style="text-align: center;" | A
| style="text-align: center;" | C/R
| style="text-align: center;" | R
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | -
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | C/R
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | I
|-
|-
| style="padding-left: 2em;" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Safety|Safety]]
| [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Interconnection|'''Interconnection''']]
| style="text-align: center;" | A
| style="text-align: center;" | A
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | R
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | R
|-
| [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Environmental,_Safety_and_Reliability_Reporting|'''Environmental, Safety, and Reliability Reporting''']]
| style="text-align: center;" | A
| style="text-align: center;" | C
| style="text-align: center;" | R
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | -
| style="text-align: center;" | -
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | I
|-
|-
| colspan="8" | [[Utility_BESS_Handbook/Handbook_Operations_and_Maintenance#Operations_and_Maintenance_Resources|'''Additional O&M Resources''']]
| [[Utility_BESS_Handbook/Handbook_Deployment_and_Integration#Deployment Resources|'''Additional Resources''']]
 
|}
|}

Latest revision as of 16:56, 19 December 2025

This is the "Deployment RACI Nav Table" template used to quickly and concisely add this RACI Nav Table to a page.

To use this, place

{{Deployment RACI Nav Table}}

in the desired location on a page.

Template preview

Chapter 4: Deployment & Integration - Outline and RACI Matrix Project Mgmt. Engineering Safety Operations Legal IT / OT / Cybersecurity Land / Environment Community Affairs Supply Chain Corporate Mgmt.
Engineering and Permitting
Site Engineering A R C C I C R - C -
System Engineering A R C C I C I - C -
Permitting A R I I C I C I C I
Factory Acceptance Test A R C C I C I - R I
Shipping and Receiving A C C R I I C I R I
Installation and Integration
Construction Management A C C R C I C C C -
Commissioning A R C C I R I I I I
Interconnection A R C C C C I - I I
Additional Resources