Difference between revisions of "Template:Deployment RACI Nav Table"

From EPRI Storage Wiki
Jump to navigation Jump to search
 
Line 28: Line 28:
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | R
| style="text-align: center;" | -
| style="text-align: center;" | -
| style="text-align: center;" | C
| style="text-align: center;" | C
Line 101: Line 101:
| style="text-align: center;" | C
| style="text-align: center;" | C
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | C
| style="text-align: center;" | R
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | I
| style="text-align: center;" | I

Latest revision as of 16:56, 19 December 2025

This is the "Deployment RACI Nav Table" template used to quickly and concisely add this RACI Nav Table to a page.

To use this, place

{{Deployment RACI Nav Table}}

in the desired location on a page.

Template preview

Chapter 4: Deployment & Integration - Outline and RACI Matrix Project Mgmt. Engineering Safety Operations Legal IT / OT / Cybersecurity Land / Environment Community Affairs Supply Chain Corporate Mgmt.
Engineering and Permitting
Site Engineering A R C C I C R - C -
System Engineering A R C C I C I - C -
Permitting A R I I C I C I C I
Factory Acceptance Test A R C C I C I - R I
Shipping and Receiving A C C R I I C I R I
Installation and Integration
Construction Management A C C R C I C C C -
Commissioning A R C C I R I I I I
Interconnection A R C C C C I - I I