Template:Deployment RACI Nav Table
Revision as of 15:21, 9 November 2023 by EulaBillaut (talk | contribs)
This is the "Deployment RACI Nav Table" template used to quickly and concisely add this RACI Nav Table to a page.
To use this, place
{{Deployment RACI Nav Table}}in the desired location on a page.
Template preview
| Chapter 4: Deployment & Integration - Outline and RACI Matrix | Project Mgmt. | Engineering | Safety | Operations | Legal | IT / OT / Cyber | Enviro. | Supply Chain | Corporate Mgmt. |
|---|---|---|---|---|---|---|---|---|---|
| Engineering and Permitting | |||||||||
| Site Engineering | A | R | C | C | I | C | C | C | - |
| System Engineering | A | R | C | C | I | C | I | C | - |
| Permitting | A | R | I | I | C | I | C | C | I |
| Factory Acceptance Test | A | R | C | C | I | C | I | R | I |
| Shipping and Receiving | A | C | C | R | I | I | C | R | I |
| Installation and Integration | |||||||||
| Construction Management | A | C | C | R | C | I | C | C | - |
| Commissioning | A | R | C | C | I | C | I | I | I |
| Interconnection | A | R | C | C | C | C | I | I | I |