US, CA, Escondido - 5 Sep 2024

From EPRI Storage Wiki
Jump to navigation Jump to search
US, CA, Escondido
Failure Incident Details
Location US, CA, Escondido
Date 5 September 2024
Power Capacity (MW) 30
Energy Capacity (MWh) 120
System Age (yr) 7.6
Battery Module
Integrator AES Energy Storage
Application
Installation Substation
Enclosure Type Container
State During Incident Undergoing maintenance
Source San Diego Union Tribune
Additional Resources Energy Storage News

One of 24 containers caught fire. Businesses adjacent to the substation or within approximately 0.25 mi were evacuated. A shelter-in-place order was issued for locations farther east. Classes were cancelled at some nearby schools. The fire started at noon on September 5, and was extinguished by 1 AM on September 6.[1][2]