Failure Event - South Korea, Yesan - 30 Aug 2019

From EPRI Storage Wiki
Jump to navigation Jump to search

Overview

Event DetailsSMW-Info-button.png
Location: South Korea, Yesan
Capacity (MW):
Capacity (MWh): 1.5
Battery Module:
Integrator:
Application: Solar Integration
Installation: Mountains
Enclosure Type: Prefab
Event Date: 30 August 2019
System Age (yr): 1.7
Extent of Damage: Fire
State During Accident: Charged, inactive
Description: The battery charging rate was increased

from 70 % to 95 %, and a fire occurred 8 days later.

Source: Social construction of fire accidents in battery energy storage systems in Korea
Additional Resources:
Note: Missing values in this table reflect unknowns.

If you have any details or corrections you would like to contribute to the database please reach out to our Storage Safety email.