Failure Event - US, CA, Moss Landing - 13 Feb 2022

From EPRI Storage Wiki
Jump to navigation Jump to search

Overview

Event DetailsSMW-Info-button.png
Location: US, CA, Moss Landing
Capacity (MW): 100
Capacity (MWh): 400
Battery Module: LG Energy Solution
Integrator:
Application: Solar Integration
Installation: Power Plant
Enclosure Type: Building
Event Date: 13 February 2022
System Age (yr): 1
Extent of Damage: Burnt racks
State During Accident: Operational
Description: The water-based suppression system leaked and led to batteries shorting and smoking. Firefighters found about 10 melted battery racks. The suppression system contained the event without the need for outside assistance. This is the second incident at this facility.
Root Cause: Integration, Construction, or Assembly
Failed Element: Balance of plant
Source: KSBW News
Additional Resources: Vistra Corp
Note: Missing values in this table reflect unknowns.